Seton phase 1 construction update

Posted by Barb Noad on November 19th, 2013 | No Comments


– 100% of all pads poured
– 98% of all the walls, columns, stairwells and elevator shafts poured
– Installed the underground mechanical and electrical in both quadrants 1 & 2 and they are working to install the underground conduits in quadrant 3
– Have poured the slab on grade in quadrant 2 and we are preparing the ground to pour the slab on grade in quadrant 1, weather permitting
– Have started to install shoring for the main floor slab in quadrant 2


 

Comments are closed.